Friday, November 25, 2011

Busy week next week!

We are planning for a busy week next week - which I love!

Monday - a fairly quiet day - Tom comes to mark the footing location pins.
Tuesday - carpenters come on-site to build the footing forms.  Meanwhile, the pool walls will be built and every thing will be prepped for the pool floor
Wednesday - rebar guys come to put in rebar for the footings, then hopefully the inspector comes  and we pour the footings immediately.  As for the pool, this is the day the pool floor will be poured.
Thursday - as long as all things go well to date, we form the foundation walls
Friday - pour the foundation walls

A busy, busy week - let's hope for some good weather!