Tuesday, February 21, 2012

HVAC Continues

A relatively quiet day today - just Andy and his crew continuing the duct work in the attic.  At this point, you can't really push the pace - as Andy said to Phil, my plumber "My pipes are thicker than yours!".  The order for all mechanical systems is HVAC first, plumbing second, electrical third, and home audio/network last before drywall.